Title
Consider awarding contracts relating to the new Operations Center to the following companies for work as outlined below:
(Strategic Goal: Develop a process and provide for coordinated expansion of the City's infrastructure that increases service levels and accommodates growth.)
1) Site preparation work in the amount of $1,063,623 to Sutton Construction, Inc. of Rock Hill.
2) Pavement work in the amount of $1,578,367 to Granite Contracting, LLC of Charlotte, N.C.
3) Utilities work in the amount of $893,650 to Showalter Construction Co., Inc. of Concord, N.C. (York, S.C. plant).
4) Consider approval for an amount not to exceed $31,200,800 for the new Operations Center, including road improvements.
Body
This work is necessary for initiating the site development for the new City Operations Center.